This project was initially identified by public bid notification in 2006, then considering technical experiences in this field, by attending mentioned bid, its expertise primary studies was started.
Regarding that this design has been bidden on behalf of National Iranian Oil Products Distribution Co. (NIOPDC) and as Engineering procurement construction (EPC) and benefited special importance due to the country’s requirement to the storage of oil materials for domestic consumption thus, it turned to one of the important national project.
After accepting financial and technical suggestion by the employer (NIOPDC) and taking order, this project was started so fast. Approximate specification of this project is as following:
Designing, preparing and purchasing, constructing and installing oil products storage tanks with the capacity of 229.410m3 and side facilities in the oil storage of Isfahan and oil storage No.2 of Mashad to method, displacement and installing two 5970 m3 ATK tanks and collecting four 450 m3  tanks in oil storage No.2 of Mashad.
Execution duration of this project was determined by the employer for 500 days.
Side works such as Bleaching, coloring, foundation design of tanks and piping connections to the available network and hydrant, earthing, lighting, bandval and cathode protection has been mentioned.  
It is to be mentioned that since this project is actively performed in oil storage, the safety of employees is highly important and therefore this project terminated without any incident.

 